Prysmian to Develop a 135km-Long HV Cable System to Be Laid at Depths of up to 950 Meters

The contract for the 135km-Long HV Cable System will be finalized within 2018, following the customary approvals from the authorities involved.

October 2, 2018

News 13Prysmian Group, world leader in the energy and telecom cable systems industry, has been awarded a new contract, worth €125 million, for an interconnection between the island of Crete and mainland Greece (Peloponnese region). The project was awarded by IPTO (Independent Power Transmission Operator), which operates the transmission system for Greece’s power grid.

The project is the first submarine electricity interconnection between the Greek island and the mainland and involves the design, supply, installation and commissioning of an HVAC (High Voltage Alternating Current) cable system composed of 150 kV three-core cables with XLPE insulation and double-wire armoring. The route extends to 135 km, reaching depth of installation up to 950 meters.

The submarine cables will be produced at the plant in Arco Felice (Naples) and will be installed at sea by the vessel Giulio Verne, which forms part of the Group’s proprietary fleet and is among the most technologically advanced in the world. Delivery and commissioning are scheduled for 2020.