Apar Industries, along with Gupta Power and CTC Global, led 22 reconductoring projects for Bihar State Power Transmission Company Limited, which have been concluded successfully in a record 7.5 months.
Mar 11, 2023
Bihar State Power Transmission Company Limited (BSPTCL) completed its 22 reconductoring projects in March 2023. Apar Industries, a major EPC group, along with Gupta Power, and CTC Global, installed over 2,450 kilometers of ACCC® Conductor on BSPTCL’s 22 reconductoring projects. BSPTCL purchase order included Casablanca and Drake size ACCC® Conductor manufactured by Apar Industries, a portion supplied by Gupta Power, and ACCC® Core supplied by CTC Global’s California and Indonesia production facilities. The projects included the installation of ACCC® Conductor on T&D setup across 20 major river crossings, 27 railway crossings, 48 major highway crossings, and 1,597 crossings traversing other T&D lines ranging from 11 kV to 765 kV.
Watch: RR Kabel | Solar Cables | Solar Plant | Renewable Energy
The 800-circuit kilometer 132 kV and 220 kV projects will increase BSPTVL’s transmission capacity by nearly 3,000 MW.
CTC Global also manufactured stainless-steel internal hardware components for 12,000 ACCC® dead ends and splices purchased by Apar from TAG corporation for these projects.
Also Read: Continuus-Properzi to Supply 250,000 Tons ETP Copper Rod Line to Adani’s Kutch Copper
Apar Industries, CTC Global, and Gupta Power expressed their elation in extending support to Bihar State Power Transmission Company and their “Quality of Power to All” initiative. The reconductoring projects started on August 2, 2022, and have been completed 20 days ahead of the set deadline, March 31, 2023, which is within 7.5 months.