Minesto AB recently successfully completed the first phase of Dragon 12 offshore installation in Vestmanna, Faroe Islands. The cable was installed in a 22-hour operation, and the next steps for the D12 installation are seabed anchoring and kite installation.
May 31, 2023
Ocean energy developer Minesto AB has completed the first phase of Dragon 12 (1.2 MW) offshore installation in Vestmanna, Faroe Islands. The 3.4 km main subsea cable was laid on the seabed, from the onshore grid connection point to the offshore installation node. After transit across the North Atlantic Ocean to Vestmanna, the cable installation work commenced and was successfully completed. A standard offshore supply vessel was adapted by Minesto’s subcontractor for the cable laying to provide a cost-efficient vessel solution for the marine operations. The cable was manufactured by JDR in the UK and loaded onto the installation vessel in Hartlepool prior to transiting to the Faroe Islands.
Also Read: NKT Bags Electric Grid Upgradation Turnkey Project in Stockholm Under 4-Year Agreement with Ellevio
The cable installation was completed in a 22-hour operation. “This cable is the most valuable component of the infrastructure, and it’s a major milestone to have it safely installed. The installation and operation were completed according to plan thanks to our team and suppliers”, said Dr Martin Edlund, CEO of Minesto. The next steps for the D12 installation are seabed anchoring and kite installation.